Intro

Location: Marrakech, Morocco
An adventure searching for the perfect derelict Riad, through the constuction itself, to the end result (insha'Allah!)

Monday, 26 December 2011

Christmas deliveries at Riad Romm'an


Its was over 20 degrees in Marrakech last week and the sun was shining.  Perfect weather for house building.  Very different to the cold, rain and wind in Scotland!


Various deliveries started arriving and being stockpiled on the surrounding streets.  These include structural steel, floor beams and massive quantities of sand and cement.


Even double doors have arrived to create a temporary site entrance onto the derb.

 
With the ground floor in and the columns up, the project was now ready for work to start on the first floor level.  

Tuesday, 20 December 2011

Rapid Progress - Week Five

It's week five already and progress has been rapid with the foundations completed and structural columns going up. 


There was some serious drama and stress this week with the need to transfer funds to the builder for purchase of materials and payment of workers.  A blockage at our Moroccan bank meant that after they had stated the transfer had been made the previous week, we discovered it hadn't and wouldn't be possible.  The builder started laying off workers and was down to a skeleton crew, then threatened to stop work completely!  The London branch of our Moroccan bank were worried about transferring money out of our account without us being there in person (in London) to verify it.  However, after a tense few days and some straight talking over the phone with the boss, they eventually relented and the funds made their way across!  Work is back on track and progress continues apace.


Many thanks to Grant Rawlings of Chic Marrakech, our project manager, for keeping us up to date with daily emails and photographs from the site.  Here's a selection of photos courtesy of Grant, from week five:
Surprisingly, potatoes are being used for the foundations of the courtyard.

Oh, no they are pebbles, not potatoes!  But why the strange metal bin set centrally into the concrete of the courtyard?  Perhaps this is actually a mould for the drain for the central fountain to enable the concreting in of the courtyard base.

Waiting for the concrete courtyard base to set.  Don't walk on it!!!

  And this hole is going to be a planter...hopefully for a new pomegranate tree?!

Ah yes, the technical bit, this picture and the one below show the cutting into the external pise walls for the columns and first floor beams. This is so that these crumbling old walls remain insitu until the building structure is complete, thereby avoiding causing instability to the neighbouring house walls.


And this is the first of the column cores which will form lovely octagonal columns for our colonnaded salon.  Next week more structural work and the first floor will being going in!

Wednesday, 7 December 2011

" أحببت هذا البيت" ("I liked that house") said the Marrakech cat


As the front of the house onto the derb is finally demolished and the last remaining wall disappears, the old house is no more!



Tuesday, 6 December 2011

Dar Cherifa


For the past seventeen years, Abdellatif Ait Ben Abdellah has been sympathetically restoring traditional riads and dars in the medina of Marrakech.  But Dar Cherifa, became something far more personal and complex.  Some of the house dates back to the sixteenth century with some nineteenth-century additions, but the building was in a poor condtion when Abdellatif took it on.  He decided to restore any detailing that still existed, otherwise walls and floors were kept bare and whitewashed.


Restoration work has revealed the large wooden beams used to support the house, some of which have been carved so they sit in harmony with the stucco-work which surrounds them.
 
Restoration work on Dar Cherifa took eight months, with an emphasis on simplicity and authenticity.  Floors and walls are finished in very straightforward fashion, with a water marble pool at the centre of the courtyard, although originally the floors would have been covered in traditional zellige.  Doors were stripped of paint, while mukarnas and stucco were also restored.


The result is an authentic restoration, presenting the dar much as it would have been four centuries ago.  The house is used as a cafe and exhibition space, so the public can come and see Dar Cherifa for themselves.  Dar Cherifa, 8 Derb Chorfa Lakbir (off Rue Mouassine), Medina, Marrakech, Morocco Tel. 212 24 42 64 63 



Monday, 28 November 2011

Week 3: Earth moving and foundation building


Just a few photos of the large amount of earth moving onto the site, in order to build up the ground level and work being done to put in the new foundations.


Saturday, 26 November 2011

A NEW FOUNDATION IS LAID

Some people say they don't believe in coincidences.  In other words, things happen for a reason.  It might just be that we don't appreciate what the reasons are, until later on.  Once we join up the dots.

 Grouting rigs pumping cement/ash mixture into the mines under our house in Scotland
As with many UK cities which expanded during the 1800's, our home city in Scotland was built over previously mined land.  Apparently 50% of the city's buildings have former mine workings below them and our neighbourhood is no exception.  Fortunately for us,  c.300 years since these mines were dug and the coal extracted, someone in their wisdom has now decided to fill in the mines, in our neighbourhood (thank you!).  Thus making sure that these old Victorian houses are built on a solid foundation.


Yesterday, 1682 miles away in North Africa, significant progress is being made with the building of Riad Romm'an.  A massive amount of new earth is now spread on site which will build up the new ground floor level.  In the photo above you can see the old perimeter walls being marked up for new structural columns which will be partly embedded 15cm into them.  In the photo's below you can see the chalked demarcation of the column points and their alignment across the house indicated by the stretched out blue wire.  The foundation stones will be arriving shortly for the chalked up foundation/column positions.


Yesterday it was election day in Morocco.  The first elections since the start of the Arab Spring in 2011 and the first to enable the direct democratic election of a prime minister in Morocco.  Without going into the detail of Moroccan politics, there is hope that this will start a new phase of democracy in the Kingdom.

It seems rather fitting therefore that the new foundations of Riad Romm'an are being laid at this time in Morocco's history.


"Those from among you will rebuild the ancient ruins, you will raise up the age old foundations, you will be called the repairer of the breach, the restorer of the streets in which to dwell." (ancient scripture)

Wednesday, 23 November 2011

A sunshine break


Yesterday the men carried on clearing the site and focused on destroying what is left of the back of the house (above) and the old salon with its arched doorway.  You can still see a bit of the old wooden canopy from the well, to the left of the archway.  Grant (our designer and project manager) tells us that the mud from the walls and old debris has turned into sludge in the rain and isn't much good for creating a base for the foundations of the house.  Most of it will have to be removed.  So far no donkeys have yet been employed to remove the debris from the site, mostly just trucks and Hondas.  Donkeys are the traditional method of construction transportation in the medina and Grant assures us that there will be plenty of opportunities for donkey action photos later on in the project.


Below are some photos from today which show the salon wall and archway completely down.


The sun came out this morning and is drying up the site.  The workmen take advantage of this to get a well earned break.  They have worked so hard and made excellent progress in such a short time.